Justice WAINWRIGHT delivered the opinion of the Court.
In this case, a general contractor and an owner dispute performance and final payment under a construction contract.
On appeal, TA argued that because Solar did not provide a lien-release affidavit, which TA argues was a condition precedent to final payment under the contract, Solar cannot recover for breach of contract. On rehearing, the court of appeals reversed the trial court's judgment, holding that the lien release provision was a condition precedent and that Solar failed to prove it complied with the lien-release provision. It rendered a take-nothing judgment in favor of TA.
We hold that the lien-release provision is a covenant, not a condition precedent to Solar's recovery on the contract. We reverse the judgment of the court of appeals, reinstate the trial court's judgment, and remand to the trial court for further proceedings consistent with this opinion.
TA entered into a contract with Solar to construct, for approximately $4 million, a retail building for use as a truck stop, restaurant, and convenience store. The contract between Solar and TA contemplates a specific sequence of events leading up to completion and final payment that is common in construction contracts. This procedure is consistent with a statutory scheme that provides contractors and builders with lien rights to secure payment for labor, but also gives owners the right to retain a percentage of the contract balance to satisfy any outstanding liens on the project if necessary.
The contractual sequence for the truck stop project is as follows: The parties agree on a construction schedule and then Solar begins work according to the schedule. On application for payment by Solar, TA is required to provide monthly progress payments. When Solar believes the construction project ready for its intended use, that it is "substantially complete," it so notifies TA. After an inspection, if TA agrees that the project is substantially complete, TA issues a "certificate of Substantial Completion" and attaches a list of items, referred to as the "punch list," to be completed or corrected before final payment.
In this case, the parties agree that the project was substantially complete in August 2000. A few weeks later, TA presented Solar with a punch list, but disputes arose over the remaining items that needed to be completed before final payment. Solar then filed a lien against the project for $472,393, and subcontractors also filed liens against the property. TA terminated Solar pursuant to the contract's "for cause" termination provision contending that, among other things, Solar had failed to keep the project lien-free and failed to complete the punch list.
By the time of trial, subcontractors filed $246,627 in liens against the project. The trial court severed the subcontractors' claims and ordered that any sums recovered by Solar, other than attorney's fees, would be held in trust for the benefit of the subcontractors' claims. The jury found in favor of Solar, and the trial court entered a judgment on the verdict in favor of Solar, awarding $392,000 in damages, which represented the balance due under the contract less an $8,000 offset to remedy all remaining "punch list" defects and omissions found by the jury.
TA appealed, and the court of appeals initially affirmed the trial court's judgment. On rehearing, however, the court of appeals reversed and rendered judgment that Solar take nothing. The court of appeals assumed that the lien-release
Whether Solar is barred from receiving the contract balance depends on whether the lien-release provision is a condition precedent to Solar's recovery for breach of contract. "A condition precedent is an event that must happen or be performed before a right can accrue to enforce an obligation." Centex Corp. v. Dalton, 840 S.W.2d 952, 956 (Tex.1992) (citations omitted); see also RESTATEMENT (SECOND) OF CONTRACTS § 224 (1981) ("A condition is an event, not certain to occur, which must occur, unless its non-occurrence is excused, before performance under a contract becomes due."); id. § 225 (noting the effects of the non-occurrence of a condition). A covenant, as distinguished from a condition precedent, is an agreement to act or refrain from acting in a certain way. Reinert v. Lawson, 113 S.W.2d 293, 294 (Tex.Civ.App.-Waco 1938, no writ). Breach of a covenant may give rise to a cause of action for damages, but does not affect the enforceability of the remaining provisions of the contract unless the breach is a material or total breach. E.g., Hernandez v. Gulf Group Lloyds, 875 S.W.2d 691, 692-94 (Tex. 1994); RESTATEMENT (SECOND) OF CONTRACTS §§ 236 cmt. a, 241, 242 cmt. a. Conversely, if an express condition is not satisfied, then the party whose performance is conditioned is excused from any obligation to perform. See Dalton, 840 S.W.2d at 956; RESTATEMENT (SECOND) OF CONTRACTS § 225.
Solar claims that the court of appeals erred in concluding that the lien-release provision is a condition precedent because it lacks conditional language normally associated with express conditions. See Criswell v. European Crossroads Shopping Ctr., Ltd., 792 S.W.2d 945, 948 (Tex. 1990). When the lien-release provision is read in context, Solar contends it constitutes a "hoop" or step that the general contractor must follow in order to collect final payment, not a condition precedent to sue and recover under the contract. Because a different and reasonable interpretation of the contract is possible, Solar argues the Court should construe the provision to prevent a forfeiture. See id. Further, the lien-release provision should not be applied as a condition precedent because its purpose—to protect TA from the possibility of having to pay twice—was accomplished by the trial court's severance of the subcontractors' claims against the project and order that the sums awarded to Solar be held in trust to pay outstanding sub-contractor liens.
TA responds that the court of appeals correctly held Solar was not entitled to the contract balance because it did not show that it complied with an express condition precedent to final payment. Section 53.085 of the Texas Property Code specifically authorizes an owner to require a lien-release affidavit as a condition of final payment. See TEX. PROP.CODE § 53.085(a),
"In order to determine whether a condition precedent exists, the intention of the parties must be ascertained; and that can be done only by looking at the entire contract." Criswell, 792 S.W.2d at 948 (citing references omitted); see also RESTATEMENT (SECOND) OF CONTRACTS § 226. "In order to make performance specifically conditional, a term such as `if', `provided that', `on condition that', or some similar phrase of conditional language must normally be included." Criswell, 792 S.W.2d at 948 (citing Landscape Design v. Harold Thomas Excavating, 604 S.W.2d 374, 377 (Tex.Civ.App.-Dallas 1980, writ ref'd n.r.e.)). "While there is no requirement that such phrases be utilized, their absence is probative of the parties intention that a promise be made, rather than a condition imposed." Id. (citing Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1, 3 (Tex.1976)). When no conditional language is used and another reasonable interpretation of the contract is possible, "the terms will be construed as a covenant in order to prevent a forfeiture." Id.
Section 14.07(A) of the contract states:
The operative language, that Solar will provide "complete and legally effective releases or waivers ... of all Lien rights" does not contain language that is traditionally associated with a condition precedent. The language preceding the lien-release provision does not make performance conditional. In the absence of any conditional
TA alleges that key language in section 14.07(B) creates the condition precedent. That section states:
While TA is correct that section 14.07(B) contains the conditional language "if," the section does not create a condition of payment to the lien-release affidavit. Rather, the condition is if TA is satisfied with the Work and the Contractual Documents, then it will recommend that Solar be paid the retainage. If TA is not satisfied with the work, then Solar "shall make the necessary corrections and resubmit the Application for Payment." Solar's obligation to provide a lien-release affidavit, and TA's obligation to pay, lie separate and apart from TA's approval of the project. If this condition were allowed to prevent Solar from suing on the contract when a building was substantially complete, then Solar would be beholden to TA to be "satisfied." In other words, if either Solar or TA disagreed with the other party's performance under the document, TA could likely sue Solar, but Solar could not sue to be paid, because TA was not satisfied under the contract.
While the Legislature's statutory scheme for contractor's lien rights provides that the parties may have chosen an alternative path, the overall scheme of the Property Code suggests interpreting the provision to avoid a forfeiture. The process for final payment common to construction contracts is complemented by statutes that protect contractors and owners in case the contractual process breaks down. First, the Texas Constitution and the Texas Property Code grant a lien in favor of contractors and builders extending to the building on which they have labored. TEX. CONST. art. XVI, § 37;
The unequal bargaining positions created by the contractor's lien rights is addressed through the mechanism of "retainage." The Property Code requires that, during the progress of work under a contract for which a contractor's lien may be claimed, the owner shall retain ten percent of the contract price. TEX. PROP.CODE § 53.101. This retainage secures the payment of any contractor or subcontractor who may assert a lien on the property in the event that the general fails to pay them. Id. § 53.102. In turn, retainage gives the owner offsetting leverage against the general contractor, whose receipt of the final ten percent of the contract balance is subject to its payment of the subcontractors in full. Thus, the contractor receives leverage over the owner in the form of the contractor's lien, and the owner receives equal leverage over the contractor in the form of the retainage. Both then have the incentive to complete the terms of the deal and the enforcement mechanisms to help ensure payment.
Finally, the Property Code allows the parties to contract for payment of the retainage to the contractor upon the owner's receipt of a lien-release affidavit. Id. § 53.085. This contractual mechanism preserves the rights of the parties but avoids the more cumbersome statutory process for retainage release. See, e.g., id. § 53.106. Essentially, the owner trades the retainage for the contractor's sworn assurance that property is lien-free. An all-bills-paid is different from a lien release, and is generally not enforceable as a condition precedent to final payment. See Lesikar Consr. Co. v. Acoustex, Inc., 509 S.W.2d 877, 880-81 (Tex.Civ.App.-Fort Worth 1974, writ ref'd n.r.e.). However, the parties may agree that, as part of the affidavit, the contractor swears that lien rights are released "conditioned on the receipt of actual payment or collection of funds...." TEX PROP.CODE § 53.085(c)(1).
Nonetheless, TA argues we should hold that the lien release is not only a condition to receive the retainage, but also a condition to fulfillment of Solar's contractual duties and thus entitlement to the contractual balance. Under this reading, Solar effectively waived its statutory and constitutional contractor's lien rights in the contract because it would not be entitled to the contractual balance until it released those rights. That view would have a contractor bargain away any leverage it had under the default rules, as an owner could simply accept the lien release and then refuse to pay, forcing the contractor to sue for the retainage. Holding that these lien-release provisions, common to construction contracts for the reasons outlined above, are conditions precedent to suit on the contract without express conditional language contravenes the lien statutes' goal of allowing the contractor or owner to avoid litigation by foreclosing on their lien or withholding the retainage. Parties are free, of course, to contract out of statutory default rules such as those established by the lien statutes and may even contractually waive constitutional rights. See Fort Worth Indep. School Dist. v. City of Fort Worth, 22 S.W.3d 831, 844 (Tex.2000) ("A party contractually waives its constitutional or statutory rights by intelligently, voluntarily, and knowingly relinquishing a known right or acting inconsistent with claiming that right.") But there would be little need for TA to bargain ex ante for a forfeiture clause in the contract in case Solar refused to provide a lien release. If the situation were to arise in which Solar was unable to assure TA that no liens would be placed on the property, the default rules already give TA the ability to withhold the retainage. A forfeiture clause would be overkill and expensive.
In this case, because both owner and contractor had a dispute over the scope of the work and subcontractors had placed liens on the property, the trial court severed the subcontractors claims. Alternatively, and ideally, Solar could have provided a conditional lien-release affidavit, which, when the trial court determined the amount owed to Solar, would have been effective once TA paid. But even under our interpretation of section 14.07 of the contract, TA will not be saddled with concerns about double-payment. The trial court will determine whether any subcontractor liens are still pending and, if so, TA may seek to discharge the liens, sue Solar for breach of the lien-release provision, or seek indemnification (either through common law or express terms of the parties contracts) from Solar for Solar's failure to pay the subcontractors.
For all of these reasons, absent clear language that a lien release is a condition precedent to a general contractor performing under the contract and receiving the contract balanced owed to it, we interpret the lien-release provision to be a covenant. We recognize that parties are free to contract as they choose, and TA should not be
For the foregoing reasons, we reverse the court of appeals' judgment and remand to the trial court for proceedings consistent with this opinion.
Justice GREEN did not participate in the decision.
TEX. PROP.CODE § 53.085(a), (c)(1).
TEX. CONST. art. XVI, § 37.